AH500 Quick Start
3. A pump
The pump is installed near the underground pool. However, the device to which the PLC
actually connects is not the pump but the control panel. Generally speaking, three digital inputs
and one digital output are connected to the digital input/output module. (Remote control x 1 (DI)
& Run x 1 (DI) & Trip x 1 (DI) & Start x 1 (DO))
4. A level meter
The level meter is installed in the underground pool, and the signal contact is connected to the
analog input module. (0~10V correspond to 0~10M. 0 V represents that the water is 0.0 meters
deep, and 10 V represents that the water is 10.0 meters deep.)
The control condition of the pump:
1. Start: If the water level inside the water tower is low and that inside the underground pool is not
low, the pump will refill the water tower.
2. Stop: If the water level inside the water tower is high, or if the water level inside the
underground pool is low, the pump stops running.
2.5
Creating Projects
After users install the hardware and understand the control logic in the example, they can write the
program.
Step 1: Open ISPSoft (StartÆProgramsÆ Delta Industrial
AutomationÆPLCÆISPSoftx.xxÆISPSoftx.xx)
The start screen of the software:
Entering the main screen of the software:
Step 2: Click
to create a project. The example is related to the water supply, and therefore the
project name is SPW. The PLC type is AHCPU530-EN, and the file path is the default path.
Finally, click
OK
.
2-12